To do list report won't show recurring tasks

C

Christine

I want to print out a to do list for resources, but no recurring tasks show
up. I have the report set to weekly and there should be a few recurring
tasks showing up, but they aren't on the report at all. How do you get
recurring tasks to show up?
 
J

JulieS

Hi Christine,

Make sure the recurring tasks are expanded in the Gantt chart view
before trying to print the report. Also ensure you have assigned your
resources.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 