To filter by resources in Project Web Access

S

Siva

Hi,
We are using Project Server 2002.
I am having a problem in filtering by a resource in a Project Web access.
For eg consider the following.
One main task(Task1) which has three subtasks(SubTask1,SubTask2,SubTask3)
and Resource A and B are working on them.
Task1
SubTask1 ResourceA
SubTask2 ResourceB
SubTask3 ResourceB


When I filter by Resource in Project Professional, am able to see main task
as well as the subtasks under which the resource is working.
so on filtering by Resource B in Project Professional displays as below.
Task1
SubTask2 ResourceB
SubTask3 ResourceB

But in web access selecting a project and filtering by a resource displays
only the subtasks to which the resource is mapped. It doesn't display the
MainTask name. So it is difficult to identify the subtask's corrosponds to
which main task.
In Project Web Access, in View A Project Screen on selecting a project and
filtering on Resource B displays the following.
SubTask2 ResourceB
SubTask3 ResourceB


So how can I filter in web access, such a way that the both Main and sub
Tasks are displayed when filtering by a resource. Kindly help me out

Thanks in advance
Siva
 