A
Arun
To Hide a Administrative Project Task.
1. open the project server database table "MSP_WEB_PROJECTS"
2. find the administrative project record
3. set the "WProj_Adminproject" field to "0" zero.
4. Login to PWA, Hide the admin project task.
5. Reset the "WProj_Adminproject" field to "1" One.
and you are all set.
1. open the project server database table "MSP_WEB_PROJECTS"
2. find the administrative project record
3. set the "WProj_Adminproject" field to "0" zero.
4. Login to PWA, Hide the admin project task.
5. Reset the "WProj_Adminproject" field to "1" One.
and you are all set.