To know about total hours

B

basim alvi

Hi,

I want to know about the total hours of particular resource in one month .

Result:

I need to know which resource i will select and know the total hours work
or Actual work of that resource in one month.

Regards

Basim Alvi
 
R

RickD

You use "select" which implies you are trying to assign a resource to a
project. In PWA highlight the project in Project Centre and then Build Team.
Selec tthe resoure(s) you are interested in and then press Availability. In
the Availability window, go to View Options and select the month range. You
can only see days or weeks in the Units. Press Set Dates. In the Details
section of the window, it will identify Availability and Work.

If you just want to review availability or assignments (work), then you can
go to the Resource Centre, select View Resource Assignments. Select the
resource(s) you want to see and press Apply. Press View Options and set the
date range for the month you want to review. Change Units to Entire Period
and on the left panel, select "All Assignments"
 