L
Langhorne
We are trying out Project Server 2007, and would like the following scenario
to work to try to match current PS03 timesheet behavior – it almost does,
with just one problem.
Projects are set up to track via “Hours of work done per periodâ€, with team
members reporting hours per task per day using “My Tasksâ€. Then each week
they would import into their timesheet, which is set up to “Create with
Projects†using “Weeks†as default tracking units. I expected the timesheet
to show the weekly total per project, based on the daily task-based input
from “My Tasksâ€. However the Top Level project line on the timesheet doesn’t
show anything. If I import the specific tasks they show up fine but also
don’t roll up to the Top Level task.
Shouldn’t the Top Level task contain totals for all the sub-tasks within it,
like it does in Project Professional? Thanks -- I appreciate any help or
thoughts you may have.
- L
to work to try to match current PS03 timesheet behavior – it almost does,
with just one problem.
Projects are set up to track via “Hours of work done per periodâ€, with team
members reporting hours per task per day using “My Tasksâ€. Then each week
they would import into their timesheet, which is set up to “Create with
Projects†using “Weeks†as default tracking units. I expected the timesheet
to show the weekly total per project, based on the daily task-based input
from “My Tasksâ€. However the Top Level project line on the timesheet doesn’t
show anything. If I import the specific tasks they show up fine but also
don’t roll up to the Top Level task.
Shouldn’t the Top Level task contain totals for all the sub-tasks within it,
like it does in Project Professional? Thanks -- I appreciate any help or
thoughts you may have.
- L