Total Cost Calculation for MS Project 2007

D

drlabon

Good Afternoon,

Here is the scenario/problem:

I have created a task (100 days duration) and assigned 2 resources t
the task at a straight time rate of 22 per hour. One resource (A) has
max unit of 100% which is assigned at 100% the total cost according th
resource sheet is 22,000. Resource (B) is at the same pay rate, sam
assignment level 100% but has a max units % of 400% (Indicating 4 grou
resources assigned at 100%. The total cost according the resource shee
still reads 22,000. How can that be?? Am I not understanding somethin
or am I missing a step?

Recap:

Resource A = Max Units 100% at 22 per hour straight time for 100 days
Total cost of 22,000

Resource B = Max Units 400% at 22 per hour straight time for 100 days
Total cost of 22,000


Why is the total cost the exact same???

thanks for any help anyone can provide
 
R

Rod Gill

Max units for a Resource is purely the maximum allocation allowed before a
Resource is flagged as over allocated.

Do you mean Max units or Peak units or what? What is the Work value for
Resource B on that Task?

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




drlabon said:
Good Afternoon,

Here is the scenario/problem:

I have created a task (100 days duration) and assigned 2 resources to
the task at a straight time rate of 22 per hour. One resource (A) has a
max unit of 100% which is assigned at 100% the total cost according the
resource sheet is 22,000. Resource (B) is at the same pay rate, same
assignment level 100% but has a max units % of 400% (Indicating 4 group
resources assigned at 100%. The total cost according the resource sheet
still reads 22,000. How can that be?? Am I not understanding something
or am I missing a step?

Recap:

Resource A = Max Units 100% at 22 per hour straight time for 100 days =
Total cost of 22,000

Resource B = Max Units 400% at 22 per hour straight time for 100 days =
Total cost of 22,000


Why is the total cost the exact same???

thanks for any help anyone can provide!


--
drlabon
------------------------------------------------------------------------
drlabon's Profile: http://forums.techarena.in/members/156649.htm
View this thread: http://forums.techarena.in/microsoft-project/1273597.htm

http://forums.techarena.in


__________ Information from ESET Smart Security, version of virus
signature database 4625 (20091120) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4625 (20091120) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
J

JulieS

Aren't both resources assigned at 100%? Setting the max. unit at
400% does not mean that the resource is **assigned** at 100%. View
the Gantt chart, split the screen (Window split) and view the
assignment units.

I also don't see how a resource can be assigned to a 100day duration
task at $22.00 per hour and have a cost of 22,000. Shouldn't there
be 800 hours of work (8 hours per day * 100 days) for a total cost
of $17,600? Do you have a ten hour day set up? It sounds like you
have a 10 hour day * 100 days for 1,000 hours of work for each
resource.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
S

Steve House

A resource with a Max Units of 400% means there are 4 individuals available
for possible assignment but assigning that resource to a task at 100% does
NOT mean that all 4 individuals are working on it. Instead it means only 1
out of the 4 is assigned to the task in question, leaving the other 3 idle
and available for assignment.
 
V

vanita

Hi

My suggestion would be that when working with people view Max. units and
assignment data in numbers instead of %, then such confusions may not arise.

To change this option go to Tools > options > schedule and change the option
of 'Show assignment units as a' to decimal.

I hope it helps.
Vanita
 
S

Steve House

That's why I always describe the assignment percentage as being a rate
variable. It's not the percentage of the resource's workday or work week
that they can spend on the project or on a task as people sometimes think.
Rather, it's an indicator of the rate at which the resource converts units
of working time spent into full-time equivalent work output. "100%" means
100 percent of the time spent is converted into useful work while "50%"
means that only half of the time actually spent appears as useful man-hours
of work.
 