Good Afternoon,
Here is the scenario/problem:
I have created a task (100 days duration) and assigned 2 resources t
the task at a straight time rate of 22 per hour. One resource (A) has
max unit of 100% which is assigned at 100% the total cost according th
resource sheet is 22,000. Resource (B) is at the same pay rate, sam
assignment level 100% but has a max units % of 400% (Indicating 4 grou
resources assigned at 100%. The total cost according the resource shee
still reads 22,000. How can that be?? Am I not understanding somethin
or am I missing a step?
Recap:
Resource A = Max Units 100% at 22 per hour straight time for 100 days
Total cost of 22,000
Resource B = Max Units 400% at 22 per hour straight time for 100 days
Total cost of 22,000
Why is the total cost the exact same???
thanks for any help anyone can provide
Here is the scenario/problem:
I have created a task (100 days duration) and assigned 2 resources t
the task at a straight time rate of 22 per hour. One resource (A) has
max unit of 100% which is assigned at 100% the total cost according th
resource sheet is 22,000. Resource (B) is at the same pay rate, sam
assignment level 100% but has a max units % of 400% (Indicating 4 grou
resources assigned at 100%. The total cost according the resource shee
still reads 22,000. How can that be?? Am I not understanding somethin
or am I missing a step?
Recap:
Resource A = Max Units 100% at 22 per hour straight time for 100 days
Total cost of 22,000
Resource B = Max Units 400% at 22 per hour straight time for 100 days
Total cost of 22,000
Why is the total cost the exact same???
thanks for any help anyone can provide