Total cost to date

D

DonnaO

How do I show total cumulative costs to date for my project (as opposed to
costs for just one task)?
 
R

Rod Gill

Have you looked at the Task Usage and Resource Usage Views and shown the
Actual Cost field? (Right Click yellow area and select Actual Cost)
--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com
 
D

Dave

Rod said:
Have you looked at the Task Usage and Resource Usage Views and shown the
Actual Cost field? (Right Click yellow area and select Actual Cost)

There is also a cumulative cost field which is probably what Rod meant.
 
A

alavinsky

Far be it from me to add much to the discussion, but I might interpret
your question a little differently....

Have you tried to show the summary task? On the Gantt Chart view, go
to Tools > Options > View, and select the Show Project Summary Task
checkbox in the bottom right.

Close out of there, and make sure the Cost (or Actual Cost - kinda
hard to say) field is showing on the Gantt Chart. Right click in the
top, and insert the appropriate field. I think you want Actual Cost -
which will show incurred costs to date. Cost will show you the
current estimate for the entire project cost as of today (including
estimates of future costs).

-A
 