S
Sdin
Group A 140.43 days
Task A 2 days
Task B 1 day
Task C 1 day
Task D 113 days
Task E 1 day
Task F 1 day
This is what is shown on my current project timeline. Where does the .43
come from in the Total Group A Duration? How do I fix it? This happens all
over my project with .38's and .13's!
Task A 2 days
Task B 1 day
Task C 1 day
Task D 113 days
Task E 1 day
Task F 1 day
This is what is shown on my current project timeline. Where does the .43
come from in the Total Group A Duration? How do I fix it? This happens all
over my project with .38's and .13's!