total duration

S

Sdin

Group A 140.43 days
Task A 2 days
Task B 1 day
Task C 1 day
Task D 113 days
Task E 1 day
Task F 1 day


This is what is shown on my current project timeline. Where does the .43
come from in the Total Group A Duration? How do I fix it? This happens all
over my project with .38's and .13's!
 
M

Mike Glen

Hi Sdin,

Welcome to this Microsoft Project newsgroup :)

You might like to see FAQ Item: 5. Default Working Hours

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 
S

Steve House [MVP]

Your tasks probably have an overlap or a gap somewhere or they straddle a
couple of shifts. Summary task durations aren't simply the sum of the
subtasks but rather are calculated as the number of working time minutes in
the Project Calendar between when the earliest starting subtask begins until
the latest finishing subtask ends. If you change your view date options so
you can see both date and time in the start and finish fields it'll probably
make more sense. If your regular workday is 8 to 5, you'll probably see the
earliest starting task begins on some date at 8am while the latest finishing
task ends about 12 noon, 140 working days later.
 