W
Wiz Kid
I have a task (Task B) that has a FNLT constraint of a date 04/03/09. It's
Early dates and Late dates are both the same - 04/03/09, but it's Total Slack
= -27 days. This obviously looked incorrect based on the EF and LF dates.
Looked at one of it's driving predecessors (Task A) and noticed that it's
Early Dates were later than its Late Dates by 27 days.
Why does the Total Slack of -27 days occur on Task B ?
Early dates and Late dates are both the same - 04/03/09, but it's Total Slack
= -27 days. This obviously looked incorrect based on the EF and LF dates.
Looked at one of it's driving predecessors (Task A) and noticed that it's
Early Dates were later than its Late Dates by 27 days.
Why does the Total Slack of -27 days occur on Task B ?