N
Nilu Talreja
Dear All,
I had two tasks Task A and Task B.
AA 7 days -Summary Task
Task A duration is 4 days - subtask
Task B duration is 3 days - subtask
While updating actual duration Task A actual duration is 3 days and
Task B also 3 days.
After updating actual start date and end date in tracking table :
It is showing like this
AA 5.88 days -Summary Task
Task A duration is 3 days - subtask
Task B duration is 3 days - subtask
Why summary task is not showing total duration of 6 days
can any help me on this.
Thanks in advance.
Bye
I had two tasks Task A and Task B.
AA 7 days -Summary Task
Task A duration is 4 days - subtask
Task B duration is 3 days - subtask
While updating actual duration Task A actual duration is 3 days and
Task B also 3 days.
After updating actual start date and end date in tracking table :
It is showing like this
AA 5.88 days -Summary Task
Task A duration is 3 days - subtask
Task B duration is 3 days - subtask
Why summary task is not showing total duration of 6 days
can any help me on this.
Thanks in advance.
Bye