Hi,
Very new to project and very frustrated. I have some tasks and all I am
trying to do is total up the costs for the budgeted amount, actual spent,
remaining/overage. I want to be able to see this via PWA. I have been able
to enter these amounts, but when I look at the baseline (budgeted) amount in
PWA I cannot get it to show me a total. any suggestions?

Andrew Brott
Wireless Internet for Central Oregon, LLC.
 
S

Sean

Andrew:

If none of the default views contains the information
you're looking for, then try building a custom view
within PWA and add the fields you want. You'll need
admin privileges. Go to Manage Views and walk yourself
through the process of creating a view, it's quite
simple. If I'm totally missing your question, shoot me
an e-mail or repost.