B
Betsy
I have 12 project files. At the task level, I want to total the clock hours
(is this Actual duration?) for each task, in each project file, and then put
the data into a chart or graph of some sort for reporting. If I use a custom
field to subtract the difference between the Finish and Start dates, it won't
take into consideration the tasks that overlap. To get this information, I
currently ask my resources when they started the task and when they finished
it and hence, I get my duration.
How do I add all the durations up across project files and then create a
graph?
(is this Actual duration?) for each task, in each project file, and then put
the data into a chart or graph of some sort for reporting. If I use a custom
field to subtract the difference between the Finish and Start dates, it won't
take into consideration the tasks that overlap. To get this information, I
currently ask my resources when they started the task and when they finished
it and hence, I get my duration.
How do I add all the durations up across project files and then create a
graph?