Trace predecessor Macro

B

Bahareh

Hello

I use Jack`s Macro for trace predecessors. It is very usefull. But I see
some errors in result. For example, task 408 is pred of task 380, but when I
run the Macro in network diagram view it is linked to the pred of task 380
(task 377). For a set of tasks this is happend. In two different Pj plan I
saw such an error.

I think that it would be perfect if you find the reason.

Ragards
 
J

JackD

The macro will not change any of the relationships.
If you have a dependency, the dependency will be there. Perhaps you have
some redundant links?
Please look in detail at the predecessors and successors to task 380, 408
and 377 and tell me what you see.

-Jack
 