B
Ben Dummar
We want to accuratley track total Delay Time to offset potential LD charges.
We have the following outline
Project Name
Delays Project Total
Bldg A
Delays Bldg A Total
Section 1
Delays Section Total
Activity 1 Delay 1
Activity 1 Delay 2
Phase 1
Activity 1
Activity 2
Activity 3
Phase 2
Phase 3
Bldg B
Delays Bldg B
.....
When we get delayed we enter a delay in the activity it affects then we have
the Total activity Delay as a predecessor to Total Bldg Delay which is a
predecessor to total Project Delay. How do we get it to accurately total all
the delay time?
We have the following outline
Project Name
Delays Project Total
Bldg A
Delays Bldg A Total
Section 1
Delays Section Total
Activity 1 Delay 1
Activity 1 Delay 2
Phase 1
Activity 1
Activity 2
Activity 3
Phase 2
Phase 3
Bldg B
Delays Bldg B
.....
When we get delayed we enter a delay in the activity it affects then we have
the Total activity Delay as a predecessor to Total Bldg Delay which is a
predecessor to total Project Delay. How do we get it to accurately total all
the delay time?