I would like to have two fields to show the number of drawings and
illustrations needed for a project. This number may possibly change several
times before they are due. What are some ways this can be shown? The areas
that do these drawings are not currently resources because they do not charge
to the project in question. Their work is represented on other schedules
with LOE tasks, not detailed at this point. However, we need a baby step
toward getting them the current information for due dates and number of items
needed. Perhaps some day the LOE schedules will become details and allow for
this information there but for now is there a good way to track this?
Thanks,
~Peggy Cornett
I would like to have two fields to show the number of drawings and
illustrations needed for a project. This number may possibly change several
times before they are due. What are some ways this can be shown? The areas
that do these drawings are not currently resources because they do not charge
to the project in question. Their work is represented on other schedules
with LOE tasks, not detailed at this point. However, we need a baby step
toward getting them the current information for due dates and number of items
needed. Perhaps some day the LOE schedules will become details and allow for
this information there but for now is there a good way to track this?
Thanks,
~Peggy Cornett