M
Michael Hansen
Hello
I have a scenario where I have the following example schedule:
- Software Acquisition
-- ERP Purchase Cost
-- ERP Annual Maintenance
-- BI Purchase Cost
-- BI Annual Maintenance
-- Consulting Services
-- Annual Support
- Design
-- Task 1
-- Task 2
- Develop
-- Task 1
-- Task 2
- etc
All the above tasks within "Software Acquisition" have a fixed cost and a
material resource associated to it. I would like to be able to enter actual
costs against these tasks in timephased manner which allows me to consume
costs against the Consulting Services tasks as it takes place. This is for a
time & materials project where we don't have costs associated against the
scoped tasks (e.g., Design, Develop, etc). I then want to be able to feed
this information into some Earned Value Management Analysis all going well.
To sum up, my problem is that I cannot manually enter the actual costs in a
timephased manner as I would expect . When doing so this actually adds
against the total cost and does not reduce the remaining cost. However, using
the 50% Complete button work OK which does not work for what I need for
consulting tasks
taking place on various days.
I hope I have explained my scenario well enough for you.
Regards
Michael Hansen
I have a scenario where I have the following example schedule:
- Software Acquisition
-- ERP Purchase Cost
-- ERP Annual Maintenance
-- BI Purchase Cost
-- BI Annual Maintenance
-- Consulting Services
-- Annual Support
- Design
-- Task 1
-- Task 2
- Develop
-- Task 1
-- Task 2
- etc
All the above tasks within "Software Acquisition" have a fixed cost and a
material resource associated to it. I would like to be able to enter actual
costs against these tasks in timephased manner which allows me to consume
costs against the Consulting Services tasks as it takes place. This is for a
time & materials project where we don't have costs associated against the
scoped tasks (e.g., Design, Develop, etc). I then want to be able to feed
this information into some Earned Value Management Analysis all going well.
To sum up, my problem is that I cannot manually enter the actual costs in a
timephased manner as I would expect . When doing so this actually adds
against the total cost and does not reduce the remaining cost. However, using
the 50% Complete button work OK which does not work for what I need for
consulting tasks
taking place on various days.
I hope I have explained my scenario well enough for you.
Regards
Michael Hansen