B
Brian
What is the best way to track actual completion dates?
You have your "Start" "Finish" dates on the project. But
how can you track the actual completion date? I have a
project date that is for example 4/21. When I put in the
actual finish date it changes the original finish date.
I need to be able to see the original start/finish dates
but also the actual completion date.
Not sure if that makes any sense, but hopefully someone
has some answers for me. The only thing that I thought I
could do was set a baseline and then track it from there.
Thanks!
You have your "Start" "Finish" dates on the project. But
how can you track the actual completion date? I have a
project date that is for example 4/21. When I put in the
actual finish date it changes the original finish date.
I need to be able to see the original start/finish dates
but also the actual completion date.
Not sure if that makes any sense, but hopefully someone
has some answers for me. The only thing that I thought I
could do was set a baseline and then track it from there.
Thanks!