J
Jule
Hi,
Do any of you actually import/input actual time into MS Project and track the actual time in MS Project for actual/planned comparision?
What would happen if you entered the actual time spent on a task and later your team decides that task should have sub-tasks... what would happen to the actual time that was entered against that task (now becomes a summary task)?
I feel that the above task's actual time should be stored and closed, and then another new task should be defined/created with its own sub-tasks for entering actual time from the time on. What is your opinion on the above scenario?
Thanks,
Jule
Do any of you actually import/input actual time into MS Project and track the actual time in MS Project for actual/planned comparision?
What would happen if you entered the actual time spent on a task and later your team decides that task should have sub-tasks... what would happen to the actual time that was entered against that task (now becomes a summary task)?
I feel that the above task's actual time should be stored and closed, and then another new task should be defined/created with its own sub-tasks for entering actual time from the time on. What is your opinion on the above scenario?
Thanks,
Jule