A
Al_at_FM
Perhaps the MS Project Server gods can help me. We have a very large project
involving both enterprise and local resources. The project has been planned
in detail using MS project and reivewed with the audit group, with audit
assigning each detailed task as either capital or expense. This way as
Actual work time is recorded, the costs (time X rate) can be summarized as
capital or expense.
Because this information is used for accounting purposes, it is most
important that the actual recorded time is not minipulated due to any
re-calculations that MS project might induce due to changes to the plan for
"planned start or finish". resource availability (+- 100%, etc.) of
requirement for resources to enter "remaining work" . What is most important
is the resources to post the actual hours worked by task, in the actual
period that the time was worked. In this regard, if the resource failed to
report actual hours in the accounting period, then we loose the
capitalization opportunity. He/she should still report the time in the
correct timeframe, but the capex is lost.
The bottomline here, is we would like to use the Time sheet facility witin
project server for time reporting against tasks... not so much for resource
balancing and planning project durations.
Pretty exhaustive message, but I would greatly appreciate any help I can
get. Thanks, Al_at_FM
involving both enterprise and local resources. The project has been planned
in detail using MS project and reivewed with the audit group, with audit
assigning each detailed task as either capital or expense. This way as
Actual work time is recorded, the costs (time X rate) can be summarized as
capital or expense.
Because this information is used for accounting purposes, it is most
important that the actual recorded time is not minipulated due to any
re-calculations that MS project might induce due to changes to the plan for
"planned start or finish". resource availability (+- 100%, etc.) of
requirement for resources to enter "remaining work" . What is most important
is the resources to post the actual hours worked by task, in the actual
period that the time was worked. In this regard, if the resource failed to
report actual hours in the accounting period, then we loose the
capitalization opportunity. He/she should still report the time in the
correct timeframe, but the capex is lost.
The bottomline here, is we would like to use the Time sheet facility witin
project server for time reporting against tasks... not so much for resource
balancing and planning project durations.
Pretty exhaustive message, but I would greatly appreciate any help I can
get. Thanks, Al_at_FM