Tracking Actual Work in Project Center 2007

R

Robert X

Hello,

The resources entered their times in their timesheets.
The timesheets are validated
The Task update has been made
The progress appears ok in Project Pro
But in the Project Center in PWA, we can't see any progress (no black bar in
the Gantt chart)
What are we missing ?

Thanks for your help!
 
D

Dale Howard [MVP]

Robert X --

You must actually publish the project using File - Publish before the
changes show up. To make sure that you remember to publish the project, we
recommend as a best practice that you process the task updates from WITHIN
Project Professional 2007 and not from PWA. When you open a project file
for which there are pending updates, the system alerts you with a dialog.
If you click Yes to view the updates, the system displays the PWA Updates
page within the Project Professional 2007 application window. From there
you can accept or reject the updates and complete the update process. When
the system finishes updating the project file in Project Professional 2007,
you can use Change Formatting to see all tasks impacted by the update
process. And then you can click File - Publish to publish the latest
schedule changes. Hope this helps.
 