R
Robert X
Hello,
The resources entered their times in their timesheets.
The timesheets are validated
The Task update has been made
The progress appears ok in Project Pro
But in the Project Center in PWA, we can't see any progress (no black bar in
the Gantt chart)
What are we missing ?
Thanks for your help!
The resources entered their times in their timesheets.
The timesheets are validated
The Task update has been made
The progress appears ok in Project Pro
But in the Project Center in PWA, we can't see any progress (no black bar in
the Gantt chart)
What are we missing ?
Thanks for your help!