Tracking against Baseline 1 - 10

C

Claus33

How can I get the "Tracking Gantt" as comparison not to "Baseline", but to
one of the additional Baselines 1 - 10? I did only found the view "Multiple
Baselines Gantt", but this option does not show the comparison to the actual
schedule.

Regards
Claus
 
J

Jim Aksel

Tools/Options.... pull the calculations tab. Click Earned Value. Change the
baseline to one of the other available baslines as the EV reference. This is
optional.

Now, Format/Bar Styles....
Scroll to the baseline bars and other items. Change the values from
Baseline to one of the other baselines. Optionally, you can add additional
baselines at the bottom of the view.

--
If this post was helpful, please consider rating it.

Jim

Visit http://project.mvps.org/ for FAQs and more information
about Microsoft Project
 
C

Claus33

Jim,

thank you, it works. I assume the first (setting Earned Value) is not
neccessary to get only the Gantt.

But it is complicate, to change alle data (Start & Finish for tasks,
milestones, summary tasks etc.). I would be a nice improvement, if the
various baselines could be selected with one click.

Best regards
Claus
 