A
Angie
I'm a newbie using Project Pro and I need help.
I have Project Server 2007 and Project Pro 2007 production.
Executive staff want to see 2 projects called "admin" and "support".
The admin and support projects will keep track of each resource’s
administrative (non working) time and time spent on support for IT systems,
(considered non project related working time).
I have a base calendar called “COA Calendar†with non working department
time for weekends, holidays, etc.
I use an enterprise resource pool and each resource has a separate resource
calendar.
Executive staff want a report all project time, admin non working and
support non working time in a report , through a master project or as a view
on PWA
Is this possible? If so, how?
I'm stumped!
Help
I have Project Server 2007 and Project Pro 2007 production.
Executive staff want to see 2 projects called "admin" and "support".
The admin and support projects will keep track of each resource’s
administrative (non working) time and time spent on support for IT systems,
(considered non project related working time).
I have a base calendar called “COA Calendar†with non working department
time for weekends, holidays, etc.
I use an enterprise resource pool and each resource has a separate resource
calendar.
Executive staff want a report all project time, admin non working and
support non working time in a report , through a master project or as a view
on PWA
Is this possible? If so, how?
I'm stumped!
Help