F
Finius Eetch
I'm having difficulty finding the best way to get % complete information back
on various milestones. I'm able to see when my entire 'project' will be done
and what % of it is done. What I want, however, is a bit more visibility.
For example I have the following milestones defined at the top of the
schedule.
Pre-Alpha
Alpha
Pre-Beta
Beta
Under that I have
Project
ProtoType
Programming
Production
Quality Assurance
As I update all the child tasks, my "Project" % complete tells me when
Project will be done. What I'd like to do is link back specific child tasks
of Prototype that make up my Pre-Alpha, Pre-Beta, Beta, Alpha milestones,
etc. to the top so when I load my schedule, I can see that I'm 'x%' towards
completion of Pre-Alpha, 'n%' towards Alpha, 'z%' towards pre-beta, etc.
Almost as if I was assigning them predeccessors - but they were 'these tasks'
assigned to this 'milestone' so report the progress total of those taskss.
What I do not want to do is move all the tasks under each milestone - which
would
give me the same information, but i'm trying to group all tasks by type, not
by deliverable, but I still want deliverable information.
Man, hope this made sense
F.E.
on various milestones. I'm able to see when my entire 'project' will be done
and what % of it is done. What I want, however, is a bit more visibility.
For example I have the following milestones defined at the top of the
schedule.
Pre-Alpha
Alpha
Pre-Beta
Beta
Under that I have
Project
ProtoType
Programming
Production
Quality Assurance
As I update all the child tasks, my "Project" % complete tells me when
Project will be done. What I'd like to do is link back specific child tasks
of Prototype that make up my Pre-Alpha, Pre-Beta, Beta, Alpha milestones,
etc. to the top so when I load my schedule, I can see that I'm 'x%' towards
completion of Pre-Alpha, 'n%' towards Alpha, 'z%' towards pre-beta, etc.
Almost as if I was assigning them predeccessors - but they were 'these tasks'
assigned to this 'milestone' so report the progress total of those taskss.
What I do not want to do is move all the tasks under each milestone - which
would
give me the same information, but i'm trying to group all tasks by type, not
by deliverable, but I still want deliverable information.
Man, hope this made sense
F.E.