J
Jessica
I have a report request that a user wants to track BCWP over time(this report will be done in Crystal Reports). If the value of BCWP = % complete x budget then I will need to track the values of % complete over time. I am told that project does not store historical data for the values of % complete as they are entered at the task level and calculated at the project level. I will definitely not be able to get my PM's to baseline each time either.
Can I create an update trigger on the % complete field in the database and insert a line into a history table that contains the % complete value and the date it was updated? Is there any other way to track this data over time? I am using Project Server 2003. Any help is appreciated. Thanks
-Jessica
Can I create an update trigger on the % complete field in the database and insert a line into a history table that contains the % complete value and the date it was updated? Is there any other way to track this data over time? I am using Project Server 2003. Any help is appreciated. Thanks
-Jessica