B
bh
Hi,
I have a project for which each task is given a fixed cost over a given
duration (resource based costs were not the most practical option in this
case). To do this I used the fixed task column since, though it is not the
intended usage, it seems the way to do this.
For example:
Project over 8 weeks
Task 1: Fixed cost = $1000 - Duration = 4 weeks [week 1 to week 4]
Task 2: Fixed cost = $1250 - Duration = 6 weeks [week 2 to week 8]
The fixed costs are accrued via pro-rating.
Now, after x amount of time, I want to enter how much has been already spent
for each task, how much work has been completed, and compare this to how much
should have been spent for that amount of work.
For example:
Task 1: Actual cost on week 2 = $600; Work completed: 50%; Scheduled cost
for that amount of work based on pro-rating: $500
I am having difficulty doing this: if I override the automated computation
of actual cost and entre the values I have for actual spending, the total
cost increases (I am not clear why).
Hopefully, my description is clear enough.
Thanks for any help or light that can be shed on this.
I have a project for which each task is given a fixed cost over a given
duration (resource based costs were not the most practical option in this
case). To do this I used the fixed task column since, though it is not the
intended usage, it seems the way to do this.
For example:
Project over 8 weeks
Task 1: Fixed cost = $1000 - Duration = 4 weeks [week 1 to week 4]
Task 2: Fixed cost = $1250 - Duration = 6 weeks [week 2 to week 8]
The fixed costs are accrued via pro-rating.
Now, after x amount of time, I want to enter how much has been already spent
for each task, how much work has been completed, and compare this to how much
should have been spent for that amount of work.
For example:
Task 1: Actual cost on week 2 = $600; Work completed: 50%; Scheduled cost
for that amount of work based on pro-rating: $500
I am having difficulty doing this: if I override the automated computation
of actual cost and entre the values I have for actual spending, the total
cost increases (I am not clear why).
Hopefully, my description is clear enough.
Thanks for any help or light that can be shed on this.