E
eganders
I have used Project for years, but have never really used it to track
costs after I finished a proposal. I would like to do so now. I tried
the approach where you select the % complete based on the project as it
was proposed. Since this is how the project was costed, it makes sense
to me. I want to get an Idea where I stand in dollars spent related
to the percent done on the original tasks in the proposal.
I went through my Project file and estimated the % done of each line
item of the original Project file used in my proposal. The problem is
that Project does not take 50% of the dollars proposed as sunk if you
say it is 50% done. If you say it is 100% done, it takes 100% of the
dollars. It only takes 100% of the dollars and 100% of the labor
hours, any percentage less is $0 and 0 work hours spent. Why is that?
I am up for suggestions on how to track it. I simply want to say that
effort A is 50% complete and have 1/2 of the work hours and 1/2 of the
dollars remaining. I can then compare what is left in the proposal
relative to what my accounting system says I actually spent.
How do I do that???
costs after I finished a proposal. I would like to do so now. I tried
the approach where you select the % complete based on the project as it
was proposed. Since this is how the project was costed, it makes sense
to me. I want to get an Idea where I stand in dollars spent related
to the percent done on the original tasks in the proposal.
I went through my Project file and estimated the % done of each line
item of the original Project file used in my proposal. The problem is
that Project does not take 50% of the dollars proposed as sunk if you
say it is 50% done. If you say it is 100% done, it takes 100% of the
dollars. It only takes 100% of the dollars and 100% of the labor
hours, any percentage less is $0 and 0 work hours spent. Why is that?
I am up for suggestions on how to track it. I simply want to say that
effort A is 50% complete and have 1/2 of the work hours and 1/2 of the
dollars remaining. I can then compare what is left in the proposal
relative to what my accounting system says I actually spent.
How do I do that???