P
Patrizio
A customer would like to track several costs at the date they are spent.
In MS Project only one default cost field is timephased, but custom cost
fields aren't timephased.
In MS Project 2007 cost resources are timephased but are summarized in the
default cost field for the task/project.
The only way we found to track several costs (not summarized) is to define
a milestone to set the date and to set custom cost fields, but the WBS will
be heavily affected.
Is there any other way to do it ?
In MS Project only one default cost field is timephased, but custom cost
fields aren't timephased.
In MS Project 2007 cost resources are timephased but are summarized in the
default cost field for the task/project.
The only way we found to track several costs (not summarized) is to define
a milestone to set the date and to set custom cost fields, but the WBS will
be heavily affected.
Is there any other way to do it ?