ProjectUser
Happy New Year's to All,
We have MS Project Termainl Server 2003 running and are trying to figure out
how to *best* capture fixed costs for IT Projects, I'm afraid Microsoft made
this product so robust that there are too many options and too few solutions.
Not only would we like to capture these costs, we'd like to report on them
(in a somewhat easy fashion) as well.
In sepcifics, we'd like to track hardware and software costs project by
project, I'll outline our proposed solutions and why we've decided not to use
them:
- Create tasks with fixed costs outlining the hardware or software cost
description
Decided not to pursue this as we would *have* to have resources book time
against these tasks and it's hard to create a task called "IBM Pro Server"
and then have time booked against it. There is also no way to report on total
hardware or total software costs in total as this infomration is strewn
around the project plan at the task level.
-Create global material resources and assign these resources at the project
level
This appears to be our best solution so far, but will crowd our global
resource pool
-Utilize the custom cost fields and create hardware and software cost columns.
We will not have accurate baseline information as these numbers don't make
it into the baseline calculations
Is our analysis flawed? There *has* to be an easy way to track these costs,
I refuse to beleive that it's this complicated.... please help!
We have MS Project Termainl Server 2003 running and are trying to figure out
how to *best* capture fixed costs for IT Projects, I'm afraid Microsoft made
this product so robust that there are too many options and too few solutions.
Not only would we like to capture these costs, we'd like to report on them
(in a somewhat easy fashion) as well.
In sepcifics, we'd like to track hardware and software costs project by
project, I'll outline our proposed solutions and why we've decided not to use
them:
- Create tasks with fixed costs outlining the hardware or software cost
description
Decided not to pursue this as we would *have* to have resources book time
against these tasks and it's hard to create a task called "IBM Pro Server"
and then have time booked against it. There is also no way to report on total
hardware or total software costs in total as this infomration is strewn
around the project plan at the task level.
-Create global material resources and assign these resources at the project
level
This appears to be our best solution so far, but will crowd our global
resource pool
-Utilize the custom cost fields and create hardware and software cost columns.
We will not have accurate baseline information as these numbers don't make
it into the baseline calculations
Is our analysis flawed? There *has* to be an easy way to track these costs,
I refuse to beleive that it's this complicated.... please help!