Hi JPenny,
You should be supplying Actual Work when tracking. If you had a
resource scheduled for 8 hours of work and enter 4 hours of Actual
Work, Project will assume the remaining 4 hours still need to be
done.
What you want ...
a view i havent
been able ot see yet that would let me enter the amount of time
the
resource worked on the a task, and automaticaly update the percent
complete, durations, project finish dates, etc.
is already there. Add Actual work to the right side(timescaled
side) of the Task Usage view through Format > Details and Select
"Actual Work". You can change the timescale through zooming in or
out and enter Actual Work on a daily or weekly basis. Entering
Actual Work will automatically update Remaining Work, Actual Cost,
Actual and Remaining Duration, % Work complete, % Complete, Actual
Start and Actual Finish.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project