Tracking Gantt - Compare to Interim Values?

J

John Castle

In Project2000, can I alter the Tracking Gantt setup so
that I can track against Interim Plan dates??
 
R

Rod Gill

Hi,

Yes. Select Format, Bar Styles and you can choose the dates that are
displayed.

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 
G

Gérard Ducouret

Hello John,

Yes, you can. Display the Tracking Gantt, then :
Format / Bar Styles...
Go down so that you find the "Baseline" grey bar. You can change the From Baseline Start To : Baseline Finish by
From Baseline Start1 (or x) To Baseline Finish1(or x).
Hope this helps,

Gérard Ducouret
 
M

Mike Glen

Hi John,

Welcome to this Microsoft Project newsgroup :)

Please see FAQ Item: 14. Viewing Multiple Baselines

FAQs, companion products and other useful Project information can be seen at
this web address: http://www.mvps.org/project/

Hope this helps - please let us know how you get on :)

Mike Glen
Project MVP
 