S
Steve Scott
Hi, we need to be ensuring that our PMs also record theirActual Start &
Actual Finish dates as well as their actual work. I note that Actual Start &
Actual Finish dates can be recorded via the Tracking/Update Tasks form or
automatically and accurately via the Task usage timesheet approach by
entering actual hours against the dates worked.
Is there any specific reason why the Actual Start & Actual Finish date
columns are not in the standard tracking gantt other than it does not give
you the flexibility to spread the work out over a protracted duration. If I
add Actual Start & Actual Finish dates into our company version of the
tracking gantt am I fundamentally doing anything wrong?
thanks in advance.
Actual Finish dates as well as their actual work. I note that Actual Start &
Actual Finish dates can be recorded via the Tracking/Update Tasks form or
automatically and accurately via the Task usage timesheet approach by
entering actual hours against the dates worked.
Is there any specific reason why the Actual Start & Actual Finish date
columns are not in the standard tracking gantt other than it does not give
you the flexibility to spread the work out over a protracted duration. If I
add Actual Start & Actual Finish dates into our company version of the
tracking gantt am I fundamentally doing anything wrong?
thanks in advance.