Tracking in Project Pro 2003 vs. Project Server

N

Newbie

Hello,
All the projects are saved in Project Server 2003, and the Enterprise
resources too.
But we have only 2 or 3 resources by project (the Project Manager
him/herself and somebody else)
They expect to enter their progress on tasks directly in Project Pro, not in
their PWA timesheet.
So what would be the best setting for the Tracking settings in PWA :
In the "Specify the default method for reporting progress" section:
- Percent of work complete
- Actual work done and work remaining
- Hours of work done per day or per week

Thanks for your advice

Newbie
 
D

Dale Howard [MVP]

Newbie --

If people are going to enter their actual progress in the Microsoft Project
plan, rather than in PWA, then it doesn't matter what methd of tracking you
select in PWA. Hope this helps.
 