J
Jean-Paul
Hello
We are currently deploying MS Project server 2003
For all our projects with have some common milestone dates that define the life of our projects
During the life of a given project, date for each of these milestones could change but we would like to track these changes and to keep an history of changes.
Do you have a solution for that? a VB macro that will export dates outside of EPMS? an external module?...
using Baseline[1-10] and start/finish[1-10] fields is obviously not a good solution for us as we can have a lot of changes.
Thanks for your hel
Jean-Paul
We are currently deploying MS Project server 2003
For all our projects with have some common milestone dates that define the life of our projects
During the life of a given project, date for each of these milestones could change but we would like to track these changes and to keep an history of changes.
Do you have a solution for that? a VB macro that will export dates outside of EPMS? an external module?...
using Baseline[1-10] and start/finish[1-10] fields is obviously not a good solution for us as we can have a lot of changes.
Thanks for your hel
Jean-Paul