R
Rachel
I'm having problems with this tracking method (% complete is working). When a
resource enters ther actual work in their assignment's page, it is
calculating the work to be much more then they submitted. For example, a
resource entered they worked 40 hours on a task (which adjustst the remaining
work to zero) and when I go to accept the task it shows the work as 64 hours
per day for 5 days (or 320 hours). This happens on a fixed work and fixed
duration task. Any idea why?
Thanks,
Rachel
resource enters ther actual work in their assignment's page, it is
calculating the work to be much more then they submitted. For example, a
resource entered they worked 40 hours on a task (which adjustst the remaining
work to zero) and when I go to accept the task it shows the work as 64 hours
per day for 5 days (or 320 hours). This happens on a fixed work and fixed
duration task. Any idea why?
Thanks,
Rachel