As per our project management process, the project plan must be approved
before the plan is published. How do you go about tracking the planning
activities that occur before the publication of the plan?
I have come up with two solutions so far:
1.Firstly, I publish the project plan containing only project management
tasks. Secondly, I publish all other tasks when the plan is approved.
2.I thought of creating a completely new project as a mean of tracking
planning activities for all our projects. This project would be structured
this way:
a. Level 1: Project1,Project2…
b. Level 2: Planning tasks.
Please let me know how you handle this.
Thanks.
Jan M.
As per our project management process, the project plan must be approved
before the plan is published. How do you go about tracking the planning
activities that occur before the publication of the plan?
I have come up with two solutions so far:
1.Firstly, I publish the project plan containing only project management
tasks. Secondly, I publish all other tasks when the plan is approved.
2.I thought of creating a completely new project as a mean of tracking
planning activities for all our projects. This project would be structured
this way:
a. Level 1: Project1,Project2…
b. Level 2: Planning tasks.
Please let me know how you handle this.
Thanks.
Jan M.