M
miao jie
Hi, Al
again when I update the current actual hours
once again, thanks a lot
have one task will last five days in original plaI meet a tracking problem when I update Project plan. for example,
hour on this task in day 1), so the status will be occured as folloday 1 2 hou
day 2 2 hou
day 3 2 hou
day 4 2 hou
day 5 2 hou
when I update 1 hour as actual hours in day 1 ( actually I just spent
task delay. and I have to spend lot of time to adjust the future plan oncday 1 1 hou
day 2 2 hou
day 3 2 hou
day 4 2 hou
day 5 2 hou
day 6 1 hou
and the extra 1 hour in day 6 will cause the resoure overallocation an
again when I update the current actual hours
the current actual hour?? it will rescue lot of time for adjust project plais there have any way to keep the future plan doesn't change when I updat
once again, thanks a lot