tracking problem on project plan update

M

miao jie

Hi, Al
I meet a tracking problem when I update Project plan. for example,
have one task will last five days in original pla
day 1 2 hou
day 2 2 hou
day 3 2 hou
day 4 2 hou
day 5 2 hou
when I update 1 hour as actual hours in day 1 ( actually I just spent
hour on this task in day 1), so the status will be occured as follo
day 1 1 hou
day 2 2 hou
day 3 2 hou
day 4 2 hou
day 5 2 hou
day 6 1 hou
and the extra 1 hour in day 6 will cause the resoure overallocation an
task delay. and I have to spend lot of time to adjust the future plan onc
again when I update the current actual hours
is there have any way to keep the future plan doesn't change when I updat
the current actual hour?? it will rescue lot of time for adjust project pla
once again, thanks a lot
 
J

James

Hi

If you are inputting Actual Work prior to the task's end-date, then it's far easier to have the task as a Fixed Duration task type. This way, the original task duration is retained, regardless of how many hours you actually worked on the previous days. Any under-booking of hours will automatically be re-scheduled across the remaining duration of the task

James.
 