Hi, can anyone show me a way to be able to show on the gant chart tracking
view or even a report the actual percentage complete for tasks,sub-projects
and the total project against the scheduled baseline percentage complete for
a given date up to the current date in a live project. Whilst the normal
tracking gant view shows the actual percentage complete/progess expressed as
a percentage the baseline is only shown as a bar alongside the actual bar
against the current date. My company expect me to be able to say "for example
we are currently 50% actually complete against a scheduled baseline of 55%
meaning we have slipped 5%" . Even if I try to do this in a report I can only
show a variance in either durations or work expressed in hours but NO
percentage. Am I asking for something that Microsoft Project cant do or do I
need to look somewhere else in the program?
any ideas would be appreciated.
regards
Rooster
view or even a report the actual percentage complete for tasks,sub-projects
and the total project against the scheduled baseline percentage complete for
a given date up to the current date in a live project. Whilst the normal
tracking gant view shows the actual percentage complete/progess expressed as
a percentage the baseline is only shown as a bar alongside the actual bar
against the current date. My company expect me to be able to say "for example
we are currently 50% actually complete against a scheduled baseline of 55%
meaning we have slipped 5%" . Even if I try to do this in a report I can only
show a variance in either durations or work expressed in hours but NO
percentage. Am I asking for something that Microsoft Project cant do or do I
need to look somewhere else in the program?
any ideas would be appreciated.