A
Arun
I have a plan that contains tasks that are unit based and also tasks with
duration based. there are Predecessors set for these tasks. The unit based
tasks are allocated to resource and duration based are not. While tracking if
there was a delay in duration based task (Task 2W1 in the example below) the
the resource can work on the other unit based work. How can this be tracked
so that the duration is utilised (for Work 2 in the example).
example:
1. Work 1
2. Task 1W1 unit based performed by A
3. Task 2W1 Duration based, 1 Day, Predecessors 2
4. Task 3W1 unit based performed by A, Predecessors 3
5. Work 2
6. Task 1W2 unit based performed by A
7. Task 2W2 duration based 1 Day, Predecessors 6
8. Task 3W2 unit based performed by A, Predecessors 7
Thanks in Advance
duration based. there are Predecessors set for these tasks. The unit based
tasks are allocated to resource and duration based are not. While tracking if
there was a delay in duration based task (Task 2W1 in the example below) the
the resource can work on the other unit based work. How can this be tracked
so that the duration is utilised (for Work 2 in the example).
example:
1. Work 1
2. Task 1W1 unit based performed by A
3. Task 2W1 Duration based, 1 Day, Predecessors 2
4. Task 3W1 unit based performed by A, Predecessors 3
5. Work 2
6. Task 1W2 unit based performed by A
7. Task 2W2 duration based 1 Day, Predecessors 6
8. Task 3W2 unit based performed by A, Predecessors 7
Thanks in Advance