Mike Cargal
No matter which defeult method for reporting progress on
tasks I select, I am only able to enter values for
percent complete and hours remaining.
I'd like to use the second option "Actual work done and
work remaining: Resources report the actual work done and
the work remaining to be done on each task.", but when I
set this option and then go to view my tasks, I still
cannot enter actual work.
tasks I select, I am only able to enter values for
percent complete and hours remaining.
I'd like to use the second option "Actual work done and
work remaining: Resources report the actual work done and
the work remaining to be done on each task.", but when I
set this option and then go to view my tasks, I still
cannot enter actual work.