Tracking Setting

R

rayis

H

Can someone explain to me the difference between the two options i
the Tracking Settings in Admin Pag

Actual work done and work remainin
Hours of work done per day or per wee

Thank
Rayi
 
M

mark.everett

Rayis -

Actual work done and work remaining use the Gantt view. For example,
you assign 30 hours of work to a resource, over 8 days duration. At
some point, the resource can enter 20 hours of work completed. The
system will calculate remaining work (10) hours. You can also allow
them to update remaining work (so if they are done in 25 hours, they
can adjust remaining work to zero, or if they think they will need 35
hours to do the work....). They don't record hours worked on any
particular day, only hours worked against the task.

Hours of work done per day or per week uses the Timesheet. Resources
enter that actual hours per day and can adjust remaining work, if you
allow it.

Hope that helps.

Mark S. Everett | PMP
 