T
tdemelle
I think I may be missing some critical concept when it comes to trackin
progress in Project.
I work in a very complex production environment with a high degree o
fluctuation in tasks. I've managed to get to the point where I hav
thousands of tasks with durations, resource assignments and dependencie
in place that are automatically being updated by a tool that imports an
merges task data from a request and task tracking tool on a dail
basis.
Durations and priorities are added to all the tasks that have bee
imported into Project where they are then leveled and massage
(dependencies removed, durations fine tuned, etc as necessary) to mode
a way to meet all known goals by their deadlines.
New multi-step, dependent tasks are imported into Project daily tha
are costed, prioritized and leveled. Work is being done throughout thi
process, sometimes ahead of requests being filed so sometimes tasks com
in that are already completed.
Here's where I run into my current Project challenges. I often fin
myself with tasks in Project that are already fully or partiall
finished ahead of the leveled schedule. When I mark them 100% complete
although the gantt bar gets filled showing 100% completion, the start
finish and duration of the task don’t change and the resource assigne
to the task remains booked into the following week on a task that i
already marked as done.
I thought I might be able to get around this by filling in “actua
duration” with the (smaller) number of actual days the task took, bu
that adjusts % complete instead of shortening the gantt bar (even whe
the initial duration is marked ‘estimated’).
I routinely get to the point where my Project is so far out of whac
with reality because resources are assigned to work that's alread
complete, I manage it by adjusting duration of completed tasks to 0
changing the project start date to today’s date and leveling to get
good forecast for what work remains. Unfortunately, apart from bein
hacky, this method undermines the ability to meaningfully track overal
% complete.
I'd really love to get my head around Project enough to be able to us
it to better manage this complex production process.
What *should* a typical status update involve? "% complete" obviously
but then also adjusting "Duration" for each task to correct for error
in the initial scheduling estimate? How then do you compare realit
against your initial estimates? Would that not more appropriately b
handled by adjusting "work"?
Thanks for any help or tips you can offer
progress in Project.
I work in a very complex production environment with a high degree o
fluctuation in tasks. I've managed to get to the point where I hav
thousands of tasks with durations, resource assignments and dependencie
in place that are automatically being updated by a tool that imports an
merges task data from a request and task tracking tool on a dail
basis.
Durations and priorities are added to all the tasks that have bee
imported into Project where they are then leveled and massage
(dependencies removed, durations fine tuned, etc as necessary) to mode
a way to meet all known goals by their deadlines.
New multi-step, dependent tasks are imported into Project daily tha
are costed, prioritized and leveled. Work is being done throughout thi
process, sometimes ahead of requests being filed so sometimes tasks com
in that are already completed.
Here's where I run into my current Project challenges. I often fin
myself with tasks in Project that are already fully or partiall
finished ahead of the leveled schedule. When I mark them 100% complete
although the gantt bar gets filled showing 100% completion, the start
finish and duration of the task don’t change and the resource assigne
to the task remains booked into the following week on a task that i
already marked as done.
I thought I might be able to get around this by filling in “actua
duration” with the (smaller) number of actual days the task took, bu
that adjusts % complete instead of shortening the gantt bar (even whe
the initial duration is marked ‘estimated’).
I routinely get to the point where my Project is so far out of whac
with reality because resources are assigned to work that's alread
complete, I manage it by adjusting duration of completed tasks to 0
changing the project start date to today’s date and leveling to get
good forecast for what work remains. Unfortunately, apart from bein
hacky, this method undermines the ability to meaningfully track overal
% complete.
I'd really love to get my head around Project enough to be able to us
it to better manage this complex production process.
What *should* a typical status update involve? "% complete" obviously
but then also adjusting "Duration" for each task to correct for error
in the initial scheduling estimate? How then do you compare realit
against your initial estimates? Would that not more appropriately b
handled by adjusting "work"?
Thanks for any help or tips you can offer