A
ans7i
I want to track how many tasks have been achieved without computing
time and/or effort factor. For example I have two main task and each has
ten sub tasks. If subtask is competed I just wanted mark as task
achieved. I don’t want to include any time or effort factor while
determining my overall complete task. So end of the day I can able to
how many task is accomplished.
For Solution I need simple formula but I am unable to figure out.
One more I need help regarding task indicators; I am not sure this
could be achievable; I need to have three indicators for each task; for
not started task (Red); orange (in progress) & green for completed task.
If all subtasks is completed parent task's indicator should change from
orange to green. Indicators should be able to change by mouse click
(without typing anything).
i only want to track task without time & effort factor; I’ll highly
appreciate if someone can lead me to right direction.
time and/or effort factor. For example I have two main task and each has
ten sub tasks. If subtask is competed I just wanted mark as task
achieved. I don’t want to include any time or effort factor while
determining my overall complete task. So end of the day I can able to
how many task is accomplished.
For Solution I need simple formula but I am unable to figure out.
One more I need help regarding task indicators; I am not sure this
could be achievable; I need to have three indicators for each task; for
not started task (Red); orange (in progress) & green for completed task.
If all subtasks is completed parent task's indicator should change from
orange to green. Indicators should be able to change by mouse click
(without typing anything).
i only want to track task without time & effort factor; I’ll highly
appreciate if someone can lead me to right direction.