J
John Sitka
Part 1.
So far the only definitative answer I can find concerning the difference
between
Default reporting method
A./ Actual work done and work remaining
vs.
B./ Hours of work done per day or per week.
1.) Gantt chart vs. Grid on the right hand side.
2.) B./ is compatable with Managed periods.
What other differences exist? I'm trying to learn of the role of protected
actuals, how they affect coping tasks,
Actual Start/ Actual Finish, status date etc.
Part2
Given A./ and B./ above
and using non managed periods
we are faced with setting
Resources should report their hours every day
Resources should report their total hours for a week
Resources should report their total hours worked during the entire time
perio set ip above
I can kind of imagine how this setting would interact with B./ as the Grid
may present itself with cells
by day/week/or period, how would it effect A./
And what is the meaning of the word "SHOULD" as in what if they don't how
long is a day? when is a day?
We are now multinational.
So far the only definitative answer I can find concerning the difference
between
Default reporting method
A./ Actual work done and work remaining
vs.
B./ Hours of work done per day or per week.
1.) Gantt chart vs. Grid on the right hand side.
2.) B./ is compatable with Managed periods.
What other differences exist? I'm trying to learn of the role of protected
actuals, how they affect coping tasks,
Actual Start/ Actual Finish, status date etc.
Part2
Given A./ and B./ above
and using non managed periods
we are faced with setting
Resources should report their hours every day
Resources should report their total hours for a week
Resources should report their total hours worked during the entire time
perio set ip above
I can kind of imagine how this setting would interact with B./ as the Grid
may present itself with cells
by day/week/or period, how would it effect A./
And what is the meaning of the word "SHOULD" as in what if they don't how
long is a day? when is a day?
We are now multinational.