S
salilu
I would like to track the work and cost associated with my MS Project task
independently using the external interface. Seems that I cannot do that in
MSP 2003.
Here is an example. I have a 5 day task with estimated work of 100 hrs. I am
not assigning any resources to this task but would like to track the work
done on it using the task level Work fields. Similarly for the same task I
would like to track the Cost INDEPENDENT of work using the task level Cost
fields. So I assign a Cost of $1000 to it using the task level Cost field.
Since I want to track the Cost and Work values independent of each other, I
turn OFF the option "Actual Costs are always computed by Microsoft Office
Project" in Tools - > Options -> Calculation window.
Now when the tasks starts I post 10 hrs Actual Work on it from a tool that
is externally interfaced. MS Project correctly sets the Actual Work to 10 hrs
and changes the Remaining Work to 90 hrs and keep the total work to 100 hrs.
So far so good. I haven't looked at the Cost fields yet since I am tracking
them indendent of Work and do not expect MS Project to make any changes to
them.
Now I post the Actual Cost of $ 200 on this task using the external
interface. I would now expect MSP to set the Remaining Cost to $800 and keep
the Cost to 1000. But Surprise Surprise --- my Cost is now $1100 and
Remaining Cost is $900.
On further analysis here is what I found--when I post the Actual Work of 10
hr, MS Project correctly calculates my Remainig work to be 90 hrs and then
changes my Remaining Cost to $900 ( in proportion Cost/Work). When I post
$200 of Actual Cost, MSP adds this $200 to the Remaining Cost of $900 and
changes the Cost to $1100. This is unexpected behavior and does not allow me
the track work and cost separately using the external interface. Is this how
the application is designed or is it a bug? How do I achieve what I want?
independently using the external interface. Seems that I cannot do that in
MSP 2003.
Here is an example. I have a 5 day task with estimated work of 100 hrs. I am
not assigning any resources to this task but would like to track the work
done on it using the task level Work fields. Similarly for the same task I
would like to track the Cost INDEPENDENT of work using the task level Cost
fields. So I assign a Cost of $1000 to it using the task level Cost field.
Since I want to track the Cost and Work values independent of each other, I
turn OFF the option "Actual Costs are always computed by Microsoft Office
Project" in Tools - > Options -> Calculation window.
Now when the tasks starts I post 10 hrs Actual Work on it from a tool that
is externally interfaced. MS Project correctly sets the Actual Work to 10 hrs
and changes the Remaining Work to 90 hrs and keep the total work to 100 hrs.
So far so good. I haven't looked at the Cost fields yet since I am tracking
them indendent of Work and do not expect MS Project to make any changes to
them.
Now I post the Actual Cost of $ 200 on this task using the external
interface. I would now expect MSP to set the Remaining Cost to $800 and keep
the Cost to 1000. But Surprise Surprise --- my Cost is now $1100 and
Remaining Cost is $900.
On further analysis here is what I found--when I post the Actual Work of 10
hr, MS Project correctly calculates my Remainig work to be 90 hrs and then
changes my Remaining Cost to $900 ( in proportion Cost/Work). When I post
$200 of Actual Cost, MSP adds this $200 to the Remaining Cost of $900 and
changes the Cost to $1100. This is unexpected behavior and does not allow me
the track work and cost separately using the external interface. Is this how
the application is designed or is it a bug? How do I achieve what I want?