Tracking

A

Angela

Is there a report to compare progress on a task in terms
of % complete. Such as your planned task is 50% complete
when you should have been 80% complete per your baseline?
 
J

JackD

Yes, This is what the earned value columns are used for.
Read the project help on earned value.

-Jack
 
A

Angela

My problem with that is I am not using cost in the
project. My bosses only want schedule and resources. There
are no costs involved.....Is there another way?
 
J

JackD

Yes,
Go to the resource sheet. Set the resource cost for each resource to $1/hr
or some other convenient amount.
Baseline.
Now all you have to do is ignore the $ sign and you will be comparing
resource hours.
I do this all the time. Consider it to be "Earned Effort" instead of earned
value.

-Jack
 