S
Steve
Hi All
I guess this must be a most basic question, however I am struggling to find
the answer.
I am new to project and currently building a plan for my company.
I have worked out the traffic light warning system for tasks at risk, on
target etc, but can only update them manually.
What I would really like to do would be for example if a task was 100 days
long each day would equate to 1% so if by day 20 only 5% work had been done
ie 5 days then that should automatically change traffic light colour to red
for behind schedule.
If this is not possible, is there a way to automatically flag up if a task
is behind schedule, I guess there will be 200+ tasks on a very important
project and I would hate to miss one because I didn't notice it.
Thanks in advance
Steve
I guess this must be a most basic question, however I am struggling to find
the answer.
I am new to project and currently building a plan for my company.
I have worked out the traffic light warning system for tasks at risk, on
target etc, but can only update them manually.
What I would really like to do would be for example if a task was 100 days
long each day would equate to 1% so if by day 20 only 5% work had been done
ie 5 days then that should automatically change traffic light colour to red
for behind schedule.
If this is not possible, is there a way to automatically flag up if a task
is behind schedule, I guess there will be 200+ tasks on a very important
project and I would hate to miss one because I didn't notice it.
Thanks in advance
Steve