N
nickc
actual We are tracking the performance to schedule of various contractors
based on a few metrics, one utilizing time on task. Once a week I will be
meeting with our contractors, and updating actual hours and resources
invested on task. I made a practice schedule and entered some actual hours
and resources on a task. The task originally had (1) resource at 100% for
3/18 – 3/20 (3 days). Creating a scenario of being told from the contractor
the task actually took 2 days, 2 people; starting on 3/18, and ending on
3/19; I went to enter the information accordingly. I entered 8 hours for
each resource on the 18, same for the 19 and entered 3/19 as the actual
finish date. Upon entering the 19th as the finish date, the hours for the
19th changed from 8 to 7 for a total duration of 1.88 days. Why?
I need to have actual time on tasks records, and cannot afford to have the
system changing the actual hours I put in. I did go back and adjust the hours
from 7 to 8, but the duration remained 1.88. My calendar is set for 8 hours
working (7:00 – 12:00, 1:00 – 4:00). None of my tasks are set for effort
driven. I understand the eed to adjust ahead of time by adding/removing
resources (ie. using effort driven tasks), but what about the back end, when
you need to enter actual (work)?
Nick
based on a few metrics, one utilizing time on task. Once a week I will be
meeting with our contractors, and updating actual hours and resources
invested on task. I made a practice schedule and entered some actual hours
and resources on a task. The task originally had (1) resource at 100% for
3/18 – 3/20 (3 days). Creating a scenario of being told from the contractor
the task actually took 2 days, 2 people; starting on 3/18, and ending on
3/19; I went to enter the information accordingly. I entered 8 hours for
each resource on the 18, same for the 19 and entered 3/19 as the actual
finish date. Upon entering the 19th as the finish date, the hours for the
19th changed from 8 to 7 for a total duration of 1.88 days. Why?
I need to have actual time on tasks records, and cannot afford to have the
system changing the actual hours I put in. I did go back and adjust the hours
from 7 to 8, but the duration remained 1.88. My calendar is set for 8 hours
working (7:00 – 12:00, 1:00 – 4:00). None of my tasks are set for effort
driven. I understand the eed to adjust ahead of time by adding/removing
resources (ie. using effort driven tasks), but what about the back end, when
you need to enter actual (work)?
Nick