M
Meeting reminder
I have a project file with over 200 tasks working fine. Recently our customer
wanted another test program implemented in the middle of the tasks. The test
engineer laid out over 50 new tasks with duration,and start,stop dates and
the predecessors under a completely different file. I tried to integrate it
into my schedule by doing a copy/paste which appeared to transfer but when I
added a predecessor from an old file task to the new task, it doesnt change
the start date. I transferred the task name, start and finish dates, and
duration in the same format. Is there a way to keep all the information and
transfer and yet still integrate with my old tasks? Or should I just
transfer the task names and manually do the start, finish, duration and
predecessors? I appreciate your help.
wanted another test program implemented in the middle of the tasks. The test
engineer laid out over 50 new tasks with duration,and start,stop dates and
the predecessors under a completely different file. I tried to integrate it
into my schedule by doing a copy/paste which appeared to transfer but when I
added a predecessor from an old file task to the new task, it doesnt change
the start date. I transferred the task name, start and finish dates, and
duration in the same format. Is there a way to keep all the information and
transfer and yet still integrate with my old tasks? Or should I just
transfer the task names and manually do the start, finish, duration and
predecessors? I appreciate your help.