Transposing View in Project Server

W

William Cornwill

I am currently trying to define a view in Project Server 2003 that performs
the following functions:

Schedule1
Part A
Task1 M/S
Task2 M/S
Task3 M/S

Schedule 2
Part B
Task1 M/S
Task2 M/S
Task3 M/S

View required in task list

Task1 Task2 Task3
Part A 100% 0% 100%
Part B 0% 0% 0%

Any ideas how this could be achieved.

William
 