J
Jason
cleHi there,
I am trying to mark some tasks for which the actual work is less than the
baseline work as 100% completed but for some obscure reasons Project does not
allow me to do so (both fields work independently between 1% - 99% complete
range, but as soon as a mark them as 100% complete, my actual work figures
become equal to my baseline work figures). I cleared the 'updating task
status updates resource status' box under the Calculation Tab in Options and
the problem persists. This means that I cannot produce report that shows
completed tasks.
Can someone please help?????
I am trying to mark some tasks for which the actual work is less than the
baseline work as 100% completed but for some obscure reasons Project does not
allow me to do so (both fields work independently between 1% - 99% complete
range, but as soon as a mark them as 100% complete, my actual work figures
become equal to my baseline work figures). I cleared the 'updating task
status updates resource status' box under the Calculation Tab in Options and
the problem persists. This means that I cannot produce report that shows
completed tasks.
Can someone please help?????